Lutra/docs/roadmap.md
danny b2bf769188 M0.9: first estimates for M1-M3 and full parity
MVP (M1-M3) about 190 agent hours, full parity about 3,300 hours (range
2,000-5,000), all marked estimated. M0 measured at about 2 hours of active
agent time. Hours per area in target-app-parity, per gap in gaps.md and
per milestone in roadmap.md; ROADMAP and README status updated.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-14 18:41:49 +02:00

1.8 KiB
Raw Blame History

Milestones

Status: M0 done, current focus M1 · Last updated: 2026-10-14

Hours are agent wall-clock hours for one agent; M0 is measured, the rest estimated.

Milestone Goal State Hours
M0 Foundation: workspace, lints, quality gate, command registry, control channel, empty window done 2026-10-14 (CI workflow written, not yet run: no remote) ~2 (measured)
M1 Editor and project: open folder, tree, tabs, editor, save, recovery, palette, settings, themes not started ~60
M2 Syntax and search: highlighting, structure, find in files, go to file/class/symbol not started ~50
M3 LSP, terminal, CLI: completion, diagnostics, go to definition, hover, rename; terminal; lutra CLI and MCP — MVP not started ~80
M4 Git: status, diff, commit, branches, log, blame, conflicts not started ~150
M5 Debugger (Xdebug via DAP), PHPUnit/Pest runner, Composer, run configurations not started ~300
M6 Own indexer and inspections; Symfony, Laravel, Shopware, WordPress support not started ~1,100

Alpha gate

Alpha is reached when these six core workflows work end to end on macOS, Windows and Linux, with save and reopen:

  1. Open a project, browse and edit files, save, recover after a crash.
  2. Navigate: go to file, class, symbol and definition; find in files.
  3. Write code with completion and diagnostics.
  4. Run commands in the integrated terminal.
  5. Commit, diff and switch branches with Git.
  6. Drive all of the above from the CLI, the control channel and MCP.

By the estimates above the alpha gate needs M1–M4 plus cross-platform verification, about 350 h.

Revision history

Date Change Summary
2026-10-14 minor M0 done; hours per milestone
2026-10-13 major Initial milestones