- theme::LIGHT next to DARK with the 10 new tokens (editor selection, active line, cursor, gutter, match, font size, tab active/modified, notice); light fg-muted, accent and error darkened for WCAG AA - theme.list, theme.systemPreference, themeChanged event when the resolved theme changes (settings.set/reset appearance.theme, or the OS preference in system mode) - desktop init script and window background from the stored setting; system mode uses a prefers-color-scheme media query for the first frame - ui/src/theme.ts applies tokens to :root and color-scheme live; editor, tabs and notice drop their var() fallbacks - Vitest WCAG AA contrast check against a Rust-maintained snapshot, DOM tests, headless control-channel test - docs: architecture Themes, parity rows, ui-parity, gaps, roadmaps Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
41 lines
2.6 KiB
Markdown
41 lines
2.6 KiB
Markdown
# Milestones
|
||
|
||
> **Status:** M0 done, M1 in progress · **Last updated:** 2026-10-16
|
||
|
||
Hours are agent wall-clock hours for one agent; M0 and M1 so far are measured, the rest estimated. Since cycle C1 (factor 0.07) M1–M3 are scaled ×0.1; M4–M6 keep their first raw estimates (multiply by ~0.1 for the calibrated value).
|
||
|
||
| Milestone | Goal | State | Hours |
|
||
|---|---|---|---:|
|
||
| M0 | Foundation: workspace, lints, quality gate, command registry, control channel, empty window | done 2026-10-14 (CI workflow written, not yet run: hosted on Forgejo, runners unknown) | ~2 (measured) |
|
||
| M1 | Editor and project: open folder, tree, tabs, editor, save, recovery, palette, settings, themes | in progress (M1.1 text, M1.2 VFS, M1.5 tree UI, M1.3 engine workspace, M1.4 desktop bridge, M1.6 tabs and editor, M1.11 message catalog, M1.9a settings backend, M1.10 themes) | ~6 (2.5 measured for M1.1–M1.6) |
|
||
| M2 | Syntax and search: highlighting, structure, find in files, go to file/class/symbol | not started | ~5 |
|
||
| M3 | LSP, terminal, CLI: completion, diagnostics, go to definition, hover, rename; terminal; `lutra` CLI and MCP — **MVP** | not started | ~8 |
|
||
| M4 | Git: status, diff, commit, branches, log, blame, conflicts | not started | ~150 |
|
||
| M5 | Debugger (Xdebug via DAP), PHPUnit/Pest runner, Composer, run configurations | not started | ~300 |
|
||
| M6 | Own indexer and inspections; Symfony, Laravel, Shopware, WordPress support | not started | ~1,100 |
|
||
|
||
## Alpha gate
|
||
|
||
Alpha is reached when these six core workflows work end to end on macOS, Windows and Linux, with save and reopen:
|
||
|
||
1. Open a project, browse and edit files, save, recover after a crash.
|
||
2. Navigate: go to file, class, symbol and definition; find in files.
|
||
3. Write code with completion and diagnostics.
|
||
4. Run commands in the integrated terminal.
|
||
5. Commit, diff and switch branches with Git.
|
||
6. Drive all of the above from the CLI, the control channel and MCP.
|
||
|
||
By the raw estimates the alpha gate needs M1–M4 plus cross-platform verification, about 350 h; calibrated with cycle C1's factor, about 35 h of agent time. Calendar time is dominated by reviews and owner decisions, not agent time.
|
||
|
||
## Revision history
|
||
|
||
| Date | Change | Summary |
|
||
|---|---|---|
|
||
| 2026-10-16 | minor | M1.9a settings backend, M1.10 themes |
|
||
| 2026-10-15 | minor | M1.11 message catalog |
|
||
| 2026-10-15 | minor | Cycle C1 review: M1–M3 hours recalibrated ×0.1, M0 CI note |
|
||
| 2026-10-15 | minor | M1.6 tabs and editor |
|
||
| 2026-10-15 | minor | M1.4 desktop bridge |
|
||
| 2026-10-14 | minor | M1 in progress |
|
||
| 2026-10-14 | minor | M0 done; hours per milestone |
|
||
| 2026-10-13 | major | Initial milestones |
|